Party Wall Process Simulator 2026 | Step by Step London
Free interactive tool

Walk through the party wall process

See every stage from planning to completion, how long each part takes, and exactly how the path changes if your neighbour consents or dissents.

Based on the Party Wall Act 1996 Real timings shown All 33 London boroughs

The party wall process is not complicated, but it is easy to underestimate how long it takes and where it can branch. Builders booked too early is one of the most common, and most expensive, mistakes. This simulator shows you the whole path before you start.

The party wall process runs in five stages: plan the works, serve the notice, wait for the 14 day response, then either proceed on consent with a schedule of condition or, on dissent, agree a party wall award before works begin. Consent can complete in about two to three weeks. A dispute usually takes four to eight weeks.

Process simulator

Pick a route, step through it

Neighbour consents
Neighbour dissents
Typical total time, notice to start2 to 3 weeks

How long it really takes

Timing is where most homeowners get caught out. The notice period alone is a legal minimum that you cannot shorten, and booking builders before it expires is a costly error.

On the consent route, where your neighbour agrees in writing, the process can wrap up in about two to three weeks. On the dissent route, where an award is needed, allow four to eight weeks from serving the notice. Complex basements or several neighbours can push that further.

The fixed legal timings. A party structure notice needs two months before works. A line of junction notice and an excavation notice need one month. After any notice, your neighbour has 14 days to respond, and silence is treated as dissent under Section 10. These periods are unchanged in 2026.

Where the path branches: consent and dissent

Everything up to the 14 day response is the same. After that, the route splits. On consent, you record a schedule of condition and proceed, with no award and no surveyor fees beyond the basics. On dissent, Section 10 brings in surveyors and a party wall award before any work can start. The simulator lets you flip between both so you can see the difference in steps and time.

Why this simulator helps

Other sites print the process as a wall of text. This lets you click through it, see the timings, and switch routes, so the plan is obvious at a glance.

Step by step

Click each stage to see what happens, who does it and how long it takes.

Both routes

Flip between consent and dissent and watch the steps and the total time change.

Real timings

The legal periods are built in, so you book builders at the right moment, not too early.

No email gate

The whole journey is on screen, free, with no form to fill before you can see it.

Three situations London homeowners face

These are representative situations, not named clients, but they show why timing matters.

Consent routeLoft, inner London

The build that started on time

An owner served early, the neighbour consented inside the 14 days, and a schedule of condition was logged the same week. The process took under three weeks, and the builders started exactly when booked. The lesson: serve early and the consent route keeps your programme on track.

Dissent routeBasement, central London

The award that took the time it needed

A basement notice met a dissent. Surveyors were appointed and an award drawn up, taking around six weeks in total. Because the owner had simulated the dissent route first, the build start was booked realistically and nothing was wasted. The lesson: plan for the dissent timeline and you avoid paying builders to wait.

Timing slipExtension, outer London

The builders booked too soon

An owner booked the build for two weeks after serving, forgetting the notice period. The neighbour dissented, an award was needed, and the builders had to be rescheduled at a cost. The lesson: the notice period is a hard minimum, so map it before you book anyone.

Frequently asked questions

If your neighbour consents promptly, the process can complete in about two to three weeks. If a dispute arises and an award is needed, allow roughly four to eight weeks from serving the notice.

Plan the works, serve the party wall notice, wait for the neighbour’s response within 14 days, then either proceed on consent with a schedule of condition, or on dissent appoint surveyors and agree a party wall award before the works and completion.

Two months for a party structure notice covering work to a shared wall, and one month for a line of junction notice or an excavation notice, before the planned start of works.

If your neighbour does not consent in writing within 14 days, a dispute is deemed to have arisen under Section 10, and the award route begins even though they never objected directly.

Important: The timings shown are typical guides, not guarantees. Actual duration depends on how quickly your neighbour responds, the works involved and the number of neighbours. The legal notice periods are minimums set by the Party Wall etc. Act 1996. Survey of Party Wall can manage the full process across London.